Hi guys.
Really hope someone can help.
We have setup a new PROD system, using BPC 7.5 MS SP8 (no patches).
NB - I cannot upgrade this level, as all development and testing to this point has used this version on the old system.
Anyway, the system appeared to install fine. ApShell DB and Cube created, etc..
I processed security successfully
I then processed each of the ApShell applications successfully.
However, when I tried to process the Dimensions, I ran in to a problem.
Basically, the process succeeds for all except one step, which is the validation of Script Logic.
I get the error:
- error querying SQL:The connection cannot be used to perform this operation. It is either closed or invalid in this context.
I have tried both validate only and Validate and Save on the logic directly, but I get the same error.
Everything else works, but this will prevent the system from being used, which is supposed to happen this weekend at the latest.
Any suggestions would be most welcome.
System design:
SQL Clustered pair
SSAS on separate server instance
SSRS on separate server
Webfolders on separate server, using \OSOFT share name - Share permissions = EVERYONE, Full Control. NTFS permissions = All 3 BPC users have Full Control
4 x Web/App servers, with NLB
Thanks in advance.