Re: Repetitive Manufacturing- PRT availability check

$
0
0

Hi Chinna,

 

Thanks for the reply..Caetano mentioned that one option is to make it as text item in the bom. so i cannot do material availability check for text item.

 

if I want to put that as stock item, then I do not want it to get backflush. once the planned order is full reduced , will this prt be released out of the dependent requirements and available for other order?

 

also regarding capacity check, you gave an idea of making it a workcenter if its critical capacity. can I make it a capacity and assign it to the machine workcenter and make this capacity relevant for scheduling in the schedulin tab? so when i go to cm25, my scheduling will be based on the capacity of the prt rather than the real machine capacity itself?