Re: Repetitive Manufacturing- PRT availability check

Caetano,

 

Thanks for the reply...now I understand that material availability check is not possible for PRT in REM.

 

but for capacity availability check of PRT, can I create PRT as a workcenter and then do leveling in MF50 using this PRT workcenter?

 

I have one stamping machine, which uses 5 molds (prt's) which make 5 different products. like this I have 7 stamping machines. when I do capacity leveling in mf50, I want to know if the PRT is available or not. is there any workaround?

 

even if i go production order route, how can I do "capacity" availability check for the prt's in CM25? CM25 goes by the main workcenter capacity, correct?