Hello Gurus,
I am trying to transfer an Old PO to Funds Centre by changing the delivery quantity in PO but the delivery date in the PO is of June 2014. I have defined the derivation strategy and system is deriving fund centre correctly but it says that Fund Centre does not exists on delivery date which is 30.06.2014. I have created fund centre from 01/01/1900 till 31/12/9999.
I tried to use FMCN it also gives the error message saying that fund centre does not exist even on current date.
For testing I posted some FI document to that fund centre and it posted.
I am not sure why it is giving error only for PO (PO has a account assignment to project/WBS).
Thanks in advance!
Regards
Rohit Goel