Hi Rupesh
We have implemented APO SNP and using optimiser result only.
I have only to look for a solution in APO to address this case.
Checked the heuristics global setting is SAP_PP_001. see the screen shot below.
As per SAP library the answer for prerequisites:
Before orders can be merged, the following prerequisites must be met:
- All orders must reference the same production process model --> OK
- All orders must be planned orders --> OK
- All orders must be synchronized, that is, the start and end times of the orders must be the same. --> NOT OK (here my SNP optimiser planned orders could be having a DIFFERENT start and end date during the month.
- All orders must be scheduled at a multi resource with storage characteristics --> Not Understood
- Synchronization must be activated in the master data of the resource --> How to do it?
Please help me to understand last 3 points on prerequisites.
Then help me to get the result in one code from RRP3.
Appreciate your help and expertise.
Thanks
Pradipta